FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: BR1053
Activity #: C6020.6020.01
Capital Project Title: Opossumtown Pike Bridge
Region: Frederick
Capital Project Status: Active Asset Type: Bridges Asset Category: Bridges
Year Identified: 2019 Est Completion Date: 9/1/2027
Capital Project Description: Bridge No. F21-01. This project will provide rehabilitation of the existing prestressed concrete box beam bridge on Opossumtown Pike over the Big Tuscarora Creek. The rehabilitation includes complete removal and replacement of the bridge superstructure and substructure repairs. The 2022 ADT at the bridge is 925 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Land
12,000 90,500
12,000 90,500
Site Improvement - NonBldg
Architect/Engineering
321,992 301,392
20,600
Construction
1,024,300
1,024,300
Inspectors - County Project Management
84,400 50,336
84,400
50,336
Total Cost:
1,583,528 351,728 102,500 1,129,300
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Federal Grants - Capital Trans from General Fund General Obligation Bonds
851,500
851,500
438,900 191,200 293,128 160,528
79,000 168,700 23,500 109,100
Total Cost:
1,583,528 351,728 102,500 1,129,300
123