FY2026-FY2031 Proposed Capital Improvement Program

Capital Project Summary

Capital Project Number: BR1052

Activity #: C6018.6018.01

Capital Project Title: Sixes Bridge Road Bridge

Region: Thurmont

Asset Type: Bridges Asset Category: Bridges

Year Identified: 2020 Est Completion Date: 12/1/2026

Capital Project Status: In Progress

Capital Project Description: Bridge No. 05-03. This project is for the rehabilitation of the existing two-span steel through truss on Sixes Bridge Road over the Monocacy River. The bridge, consisting of two 119-foot spans, was built in 1890 and last rehabilitated in 1995. The project will include replacement of deteriorated and damaged structural members, repoint and repair of existing stone masonry substructure units, and complete cleaning and painting of structural steel. The 2007 ADT at the bridge is 180 vehicles per day.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2026

2027

2028

2029

2030

2031 Costs After

Land

23,504 67,704

23,504 67,704

Site Improvement - NonBldg

Architect/Engineering

264,700 243,900

20,800

Construction

2,680,100

2,680,100

Inspectors - County Project Management

268,100 58,700

268,100

58,700

Total Cost:

3,362,808 393,808 2,969,000

Funding Schedule:

Project Total

Prior Budget

Categories

2026

2027

2028

2029

2030

2031 Costs After

Federal Grants - Capital Trans from General Fund General Obligation Bonds

2,222,300

2,222,300

795,300 345,300 450,000

345,208

48,508 296,700

Total Cost:

3,362,808 393,808 2,969,000