FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: PR2013
Activity #:
Capital Project Title: Ballenger Creek Park Synthetic Turf Field Carpet Replacement
Region: Frederick
Asset Type: Parks & Recreation Asset Category: Parks & Recreation
Year Identified: 2023 Est Completion Date: 12/1/2026
Capital Project Status: Active
Capital Project Description: The Foreman Field at Ballenger Creek Park was completed and opened to the public in the fall of 2014. The synthetic turf carpet has an average life span of 8 to 10 years. This project will include the removal/disposal of existing turf carpet and installing a new one. Sewn-in field line markings will match existing ones. Existing infill will be supplemented with Coolplay infill to reduce the temperature of the field surface during hot days.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Inspectors - County Project Management
20,000 20,000
20,000 20,000
Capital - Furniture / Equipmen 1,060,800
1,060,800 1,100,800
Total Cost:
1,100,800
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Trans from General Fund General Obligation Bonds
1,100,800
1,100,800
0
Total Cost:
1,100,800
1,100,800