FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: ED1041 Capital Project Title: Brunswick HS: Replacement Asset Category: Board of Education Asset Type: New/Modernizations Capital Project Status: Active
Activity #: C1802.1802.02 Region: Est Completion Date: 8/31/2030 Year Identified: 2019
Capital Project Description: Brunswick HS was originally constructed in 1965 with additions in 1979, 1983 and 1993. Other than a small 2,000 sq ft renovation in 1983, there have been no other significant improvements to the building. The Board of Education conducted a feasibility study and approved a replacement school in 2019. The replacement school is anticipated to have state rated capacity for approximately 1,000 students and be constructed on the same site. Pre-design funding will help determine the design and phasing of the project to accommodate students on site while a new building is constructed. Limited planning is anticipated for May 2025 when the State IAC finalizes their 100% allocations for the FY2026 budget.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031
Costs After
Studies / Surveys
0
Site Work- State's Share
10,426,147 8,190,444 48,481,550 1,975,481 10,845,331 7,248,412 64,466,861 4,024,519
2,225,512 5,476,597
8,200,635
A&E - State's Share
2,713,847
Construction - State's Share Equipment - State's Share Site Work - County's Share
37,549,852
8,710,635
2,221,063 1,975,481
10,845,331 4,534,565
A&E - County's Share
2,713,847
Construction - County's Share Equipment - County's Share
5,146,527 34,249,513 21,289,365
3,781,456 4,024,519
Studies - County's Share
186,008
186,008 186,008
Total Cost: 155,844,753
5,427,694 28,228,532 80,000,000 30,000,000 12,002,519
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031
Costs After
Trans from General Fund Trans from General Fund- BOE Paygo Trans from Impact Fee
6,109,295 44,079,737
134,565
250,000
200,000
2,297,365
3,227,365
2,579,282 14,950,942 26,549,513
5,492,000 4,186,008
800,000
4,500,000
192,000
Trans from School Construction
186,008
4,000,000
General Obligation Bonds Recordation Tax Bonds MD BOE - Cash Forward Funding
25,879,572 3,000,000 67,098,141
4,525,481
14,800,000
6,554,091
3,000,000
2,713,847
7,702,109 45,750,487
8,710,635
2,221,063
Total Cost: 155,844,753
186,008
5,427,694 28,228,532 80,000,000 30,000,000 12,002,519
219