FY2024-FY2029 Adopted Capital Improvement Program

Capital Project Summary

Capital Project Number: ED1047

Activity #: C1702.1702.02

Capital Project Title: Crestwood MS: Addition

Region: Frederick

Asset Type: New/Modernizations Asset Category: Board of Education

Year Identified: 2021 Est Completion Date: 8/31/2024

Capital Project Status: Active

Capital Project Description: Crestwood Middle School opened in 2004 with a SRC of 600 students and an oversized core space, with a footprint for a future addition. The school is currently operating at 83% of state rated capacity, but growth is expected in the area over the next ten years, including within the City of Frederick. This will necessitate the need for additional middle school seats to help balance enrollments, such as with Monocacy Middle which is at 99% SRC. The Crestwood Middle School project will utilize nearly the same design as the Oakdale Middle Addition project and will increase the capacity of the existing school by 318 students, adding about 22,000 SF to the existing building. The Crestwood Middle School project is expected to begin construction in the summer of 2023 and open in the summer of 2024.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2024

2025

2026

2027

2028

2029 Costs After

Site Work - County's Share

1,496,649

1,496,649

A&E - County's Share 569,000 569,000 Construction - County's Share 9,282,542 158,000 9,124,542 Equipment - County's Share 500,000 500,000 Total Cost: 11,848,191 727,000 11,121,191

Funding Schedule:

Project Total

Prior Budget

Categories

2024

2025

2026

2027

2028

2029 Costs After

Trans from Impact Fee

11,848,191 727,000 11,121,191 11,848,191 727,000 11,121,191

Total Cost: