FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: ED1030 Capital Project Title: Blue Heron ES Asset Type: New/Modernizations Asset Category: Board of Education
Activity #: C1607.1607.02
Region: New Market
Year Identified: 2013 Est Completion Date: 8/31/2021
Capital Project Status: Active
Capital Project Description: The new Blue Heron Elementary School is located in the Hamptons West neighborhood of the Linganore PUD. The school is designed for students in grades Pre-K through 5 and will offer the Pyramid Program currently housed at Spring Ridge Elementary. Blue Heron Elementary School will have a state rated capacity of 705 students. It is the first school that will utilize the updated FCPS elementary prototype design. The new school is expected to open and occupied in August of 2021. *Current Budget reflects state funding source change only.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Site Improvement - NonBldg
0 0 0 0
Architect/Engineering
Construction
Capital Approp Equipment Site Work- State's Share
2,760,227 2,760,227 Construction - State's Share 14,785,454 14,134,893 650,561 Site Work - County's Share 2,781,982 2,781,982 A&E - County's Share 2,082,704 2,082,704 Construction - County's Share 19,216,557 19,867,118 -650,561 Equipment - County's Share 2,100,000 2,100,000 Total Cost: 43,726,924 43,726,924
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
MD BOE - Capital Project Trans from General Fund Trans from Impact Fee
17,545,681 9,318,235 8,227,446
0
11,632,466 11,632,466 Trans from School Mitigation 12,419,363 13,069,924 -650,561 General Obligation Bonds 2,129,414 2,129,414 Bonds - Forward Funding 0 MD BOE - Cash Forward Funding 0 7,576,885 -7,576,885 Total Cost: 43,726,924 43,726,924