FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: ED1024
Activity #: C1613.1613.02
Capital Project Title: Middletown Co-located ES/MS replacement
Region: Middletown
Asset Type: New/Modernizations Asset Category: Board of Education
Year Identified: 2021 Est Completion Date: 8/31/2029
Capital Project Status: Active
Capital Project Description: The Board of Education approved the feasibility study recommendation for a 157,374 gross square feet co-located replacement school, in February 2023. The new co-located school will have educational spaces for an elementary school program, serving grades 3 through 5, and a middle school program, serving grades 6 through 8, entirely separate but co located in one facility. Design for the co-located school is expected to take roughly two years. Following occupancy of the new co-located school building, the existing elementary and middle school buildings will be demolished, followed by the completion of site vehicular circulation, parking, and playfield development.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Studies / Surveys
400,000 400,000
Site Improvement - NonBldg
0 0 0 0 0
Architect/Engineering
Construction
Capital Approp Equipment Capital Approp - Studies Site Work- State's Share
7,603,891 5,129,000
7,603,891
A&E - State's Share
5,129,000
Construction - State's Share 43,112,569
40,020,481 3,092,088
Site Work - County's Share
5,625,803 3,287,215
5,625,803
A&E - County's Share
3,287,215
Construction - County's Share 28,607,614
21,549,490 7,058,124
Equipment - County's Share Studies - County's Share
3,000,000
3,000,000
0
Total Cost:
96,766,092 400,000 8,416,215 13,229,694 61,569,971 13,150,212
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
MD BOE - Capital Project Trans from General Fund Trans from Impact Fee
5,129,000
5,129,000
20,819,540 400,000 3,122,215 2,875,803 14,421,522
1,415,000 8,500,000
165,000 250,000 1,000,000
Trans from School Construction
2,500,000 3,000,000 3,000,000
General Obligation Bonds Bonds - Forward Funding MD BOE - Cash Forward Funding
10,186,092
3,127,968 7,058,124
0
50,716,460
7,603,891 40,020,481 3,092,088
Total Cost:
96,766,092 400,000 8,416,215 13,229,694 61,569,971 13,150,212
259
Made with FlippingBook - professional solution for displaying marketing and sales documents online