FY2023-FY2028 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG1158
Activity #:
Capital Project Title: Work Release Parking Lot Expansion
Region: Frederick
Asset Type: Other Asset Category: General Government
Year Identified: 2021 Est Completion Date: 8/1/2024
Capital Project Status: Active
Capital Project Description: Due to the anticipated increase in vehicular traffic from the upcoming Detox Services project, additional parking will be required at the Work Release Center. This project will include an axillary parking lot, on the adjacent side of Marcies Choice Lane, and will provide approximately 30 additional parking spaces.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Site Improvement - NonBldg
33,518 55,863 368,311 67,035 27,931 558,244 5,586
33,518 55,863 368,311 67,035 27,931 558,244 5,586
Architect/Engineering
Construction
Construction - IIT Infrastruct
Inspectors - County Project Management
Total Cost:
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
General Obligation Bonds
558,244 558,244
558,244 558,244
Total Cost: