Capital Project Summary
Capital Project Number: MP1001
Activity #: C9000.9000.02
Capital Project Title: Frederick Municipal Airport
Region: Frederick
Capital Project Status: Active Asset Type: City of Frederick Asset Category: Municipalities
Year Identified: 2010 Est Completion Date: 6/30/2028
Capital Project Description: Design and construct improvements to Frederick Municipal Airport as outlined in the Airport Master Plan, stage I & II improvements. Updated to reflect current cost and FAA funding. The Federal Government share is 90%, the State share is 5.0% and the County and City shares are both 2.5%. ONLY the county portion is being shown.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Capital Appropriations 0 Capital Approp - Other Parties 1,610,368 906,757 185,833
25,000 152,778 25,000 152,778
15,000 150,000 175,000 15,000 150,000 175,000
Total Cost:
1,610,368 906,757 185,833
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from General Fund General Obligation Bonds
1,528,283 824,672 185,833
25,000 152,778
15,000 150,000 175,000
82,085
82,085
Total Cost:
1,610,368 906,757 185,833
25,000 152,778
15,000 150,000 175,000