FY2023-FY2028 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: ED5001
Year Identified: 2010 Est Completion Date: Region: Countywide Activity #: C1000.1000.02
Capital Project Title: Systemics - Generic Asset Type: Systemic Asset Category: Board of Education
Capital Project Status: Active
Capital Project Description: This project serves as the budget for all systemics including such projects as roof, mechanical, paving, flooring, playground replacements, and other projects and may be re-allocated to sub-projects as needed for recording and tracking purposes.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Capital Appropriations
0
Construction - State's Share 81,000 -2,194,000 2,275,000 Construction - County's Share 12,434,000 2,694,000 2,915,000 1,365,000 1,365,000 1,365,000 1,365,000 1,365,000 Total Cost: 12,515,000 500,000 5,190,000 1,365,000 1,365,000 1,365,000 1,365,000 1,365,000
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
MD BOE - Capital Project Trans from General Fund General Obligation Bonds MD BOE - Cash Forward Funding
2,047,000
2,047,000
762,600
80,000 250,000
86,520
86,520
86,520
86,520
86,520
9,477,400 420,000 2,665,000 1,278,480 1,278,480 1,278,480 1,278,480 1,278,480
228,000
228,000
Total Cost:
12,515,000 500,000 5,190,000 1,365,000 1,365,000 1,365,000 1,365,000 1,365,000