Capital Project Summary
Capital Project Number: WS1047
Activity #: 21281.1206.01
Capital Project Title: Maintenance Building Expansion/Relocation
Region: Countywide
Capital Project Status: In Progress Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2019 Est Completion Date: 12/31/2023
Capital Project Description: This project involves preparation of a Facility Plan to identify and analyze possible options to expand or relocate the DUSWM Maintenance Building/Operation currently located on Marcies Choice Lane. Project includes funds to execute approved options which could include purchase and development of a new site, redevelopment of the existing site, renovation of the existing building, or a combination of these options.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
NonCapital Furniture / Equipment
950,000
950,000
Land
1,000,000 1,000,000 985,000 985,000
Architect/Engineering
Construction - County Funded 11,999,000
11,999,000
Inspectors - County Project Management
250,000 150,000 280,000 280,000 570,000 570,000 16,034,000 2,985,000
100,000
Overhead
Total Cost:
12,099,000 950,000
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from W/S Cash Fund Enterprise Fund Bonds
1,659,490 1,443,500 14,374,510 1,541,500 16,034,000 2,985,000
120,990
95,000
11,978,010 855,000 12,099,000 950,000
Total Cost: