Capital Project Number: WS1017
Activity #: 11189.1105.01
Capital Project Title: Water Storage Tank Improvements
Region: Countywide
Capital Project Status: In Progress Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2015 Est Completion Date: 6/30/2027
Capital Project Description: Project includes installation of mixing and/or aeration systems in five existing water storage tanks to assist in removal of potential disinfection byproducts. Tanks are Monrovia, East County, Urbana Tank No. 1, Point of Rocks, Nightingale, Jordan and Hannover. Tank improvements are complete for the East County and Urbana tanks, Monrovia is currently under construction. Additional funds are being requested for FY25 & FY26 in case testing indicates the need to add improvements to other tanks.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Construction - County Funded 1,485,000 375,000 370,000 370,000 370,000 Inspectors - County 196,000 76,000 40,000 40,000 40,000 Overhead 98,000 38,000 20,000 20,000 20,000 Capitalized Interest Expense 12,000 12,000 Total Cost: 1,791,000 501,000 430,000 430,000 430,000
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from W/S Cash Fund Enterprise Fund Bonds
12,000
12,000
1,779,000 489,000 430,000 430,000 430,000 1,791,000 501,000 430,000 430,000 430,000