FY2023-FY2028 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1063
Activity #:
Capital Project Title: East County BPS Third Pump Addition
Region: Countywide
Capital Project Status: Active Asset Type: Capacity Asset Category: Water & Sewer
Year Identified: 2021 Est Completion Date: 11/4/2023
Capital Project Description: Design and install a third County pump with VFD controls and integration at the existing East County BPS.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Architect/Engineering
75,000 330,150 15,000 25,000 20,000 465,150
75,000
Construction - County Funded
330,150 15,000 10,000 10,000
Inspectors - County Project Management
15,000 10,000
Overhead
Total Cost:
100,000 365,150
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from W/S Cash Fund Enterprise Fund Bonds
465,150
100,000 365,150
0
Total Cost:
465,150
100,000 365,150
193