FY2023-FY2028 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1062
Activity #:
Capital Project Title: New Design WTP Sludge Thickener No. 2
Region: Countywide
Capital Project Status: Active Asset Type: Capacity Asset Category: Water & Sewer
Year Identified: 2021 Est Completion Date: 6/30/2024
Capital Project Description: Design and Construct second Gravity Sludge Thickener tank at the New Design Road Water Treatment Plant. Existing tank was constructed under Contract 026G-W and space was provided for this future tank.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Architect/Engineering
316,300
316,300
Construction
3,153,820
3,153,820
Inspectors - County Project Management
163,000 41,300 81,500
163,000 20,000 40,000
21,300 41,500
Overhead
Total Cost:
3,755,920
379,100 3,376,820
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from W/S Cash Fund Enterprise Fund Bonds
379,100
379,100
3,376,820 3,755,920
3,376,820
Total Cost:
379,100 3,376,820
192
Made with FlippingBook - Online magazine maker