Capital Project Number: PR2012
Activity #:
Capital Project Title: Rocky Ridge Landing Master Plan
Region: Thurmont
Asset Type: Parks & Recreation Asset Category: Parks & Recreation
Year Identified: 2022 Est Completion Date: 12/31/2028
Capital Project Status: Active
Capital Project Description: This property has been owned by Frederick County since 1976. A Park Master Plan is a general guide for appropriate park uses and their approximate location within a specific park site. The plan serves as a long-range vision for future development and programming of the park and its resources. The plan is conceptual in nature and not intended to address detailed issues related to engineered site design or park operations. Typical items addressed in a Park Master Plan include planning park elements, natural and cultural resources, and general design concerns.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Studies / Surveys Project Management
225,000 30,000 255,000
225,000 30,000 255,000
Total Cost:
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from Parks Acquisition
255,000 255,000
255,000 255,000
Total Cost: