FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: PR1023 Capital Project Title: Othello RP - Ph 2 Asset Type: Parks & Recreation Asset Category: Parks & Recreation Capital Project Status: In Progress
Activity #: C7111.7111.01
Region: Brunswick
Year Identified: 2020 Est Completion Date: 7/31/2027
Capital Project Description: Construction of the Phase I Development was completed in FY2021. The Phase II Development project will focus on providing facilities/amenities to address sports and recreational needs of County residents. Potential new amenities could include shelters, trails, parking lots/roadways and a community center up to 30,000 SF.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Site Improvement - NonBldg
195,056 195,056 839,334 839,334
Architect/Engineering
Construction
10,714,200
5,357,100 5,357,100
Construction - IIT Infrastruct
60,300 276,000 162,015 757,000 88,900
60,300
Inspectors - County Project Management
138,000 138,000
52,015
55,000
55,000 757,000 88,900
Capital - Furniture / Equipmen
Capital - IIT Hardware
Total Cost:
13,092,805 1,086,405 5,610,400 6,396,000
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Trans from Parks Acquisition General Obligation Bonds
5,692,805 1,086,405 1,800,400 2,806,000
0
Recordation Tax Bonds
7,400,000
3,810,000 3,590,000
Total Cost:
13,092,805 1,086,405 5,610,400 6,396,000