FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: GG2038
Activity #:
Capital Project Title: Montevue Campus Renovation and Reconfiguration
Region: Frederick
Asset Type: Other Asset Category: General Government
Year Identified: 2020 Est Completion Date: 12/31/2030
Capital Project Status: Active
Capital Project Description: A feasibility study of the 331 Montevue campus site was completed in June, 2018. The study included analysis of the existing site and buildings with a primary focus on the Administration and District Crew Buildings. An analysis of overall traffic flow was also included in the study. The study concluded that a modification to 331 Montevue Lane would be warranted to better serve the current and future staffing requirements of the Division of Public Works. It was also concluded that a reconfiguration of the existing traffic pattern would be warranted due to the relocation of the refueling station, which has been previously approved under a separate project. The project also includes an expansion of the existing fleet space along with electrical system upgrades to accommodate capacity needs for temperature controls and EV charging while electric vehicles are at the shop. The study included construction cost estimates, which have been incorporated.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
NonCapital Furniture / Equipment
283,600
283,600
Site Improvement - NonBldg
142,900 803,200
142,900 803,200
Architect/Engineering
Construction
5,428,300
5,428,300
Construction - IIT Infrastruct
163,100 187,500 130,400
163,100 187,500 65,200 85,500
Inspectors - County Project Management Capital - IIT Hardware
65,200
85,500
Total Cost:
7,224,500
1,011,300
6,213,200
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
General Obligation Bonds
7,224,500 7,224,500
1,011,300 1,011,300
6,213,200 6,213,200
Total Cost:
48