FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1213
Activity #:
Capital Project Title: Crestview White Rock SPS
Region: Countywide
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2025 Est Completion Date: 6/30/2028
Capital Project Description: Design and Construct Sewage Pump Stations and associated Sewage Force Mains to replace the Crestview WWTP and the White Rock WWTP. These proposed SPS ’ s will combine their effluent and flow to the Tuscarora Creek Sewer Interceptor where wastewater treatment will be achieved by the Ballenger McKinney WWTP. Thus eliminating the Operating and Maintenance of the two small system WWTP ’ s.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Architect/Engineering
2,200,000
1,100,000 1,100,000
Construction - County Funded 5,500,000
5,500,000
Inspectors - County Project Management
165,000 550,000 825,000
165,000
220,000 220,000 110,000 330,000 330,000 165,000 1,650,000 1,650,000 5,940,000
Overhead
Total Cost:
9,240,000
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Enterprise Fund Bonds
9,240,000 9,240,000
1,650,000 1,650,000 5,940,000 1,650,000 1,650,000 5,940,000