FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1211
Activity #:
Capital Project Title: Point of Rocks Sewer Line Replacement
Region: Brunswick
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2025 Est Completion Date: 6/30/2027
Capital Project Description: Replacement (as defined by aging of pipe) or lining (as defined by the Inflow and Infiltration Report prepared by Duke's) of sewer pipe within Point of Rocks.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Architect/Engineering
100,000
100,000
Construction - County Funded 1,000,000
1,000,000
Inspectors - County Project Management
30,000 20,000 30,000
30,000 20,000 30,000
Overhead
Total Cost:
1,180,000
1,180,000
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Enterprise Fund Bonds
1,180,000 1,180,000
1,180,000 1,180,000
Total Cost:
190