FY2026-FY2031 Proposed Capital Improvement Program

Capital Project Summary

Capital Project Number: WS1204

Activity #:

Capital Project Title: Influent and effluent sewer meters at all WWTPs

Region: Countywide

Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer

Year Identified: 2025 Est Completion Date: 6/30/2031

Capital Project Description: Ensure installation of influent and effluent sewer meters at all wastewater treatment facilities. All of the existing wastewater facilities have effluent meters, but may need to be upgrade to current standards. Some but not all of the existing wastewater facilities have influent meters, or may need to be updated to current standards. The collection of data at these control points will be useful to the understanding of the operations of these systems, as well as aiding the inflow and infiltration studies of the associated collection systems. initial phase = overall assessment of existing WWTPs 4 years for installation.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2026

2027

2028

2029

2030

2031 Costs After

Architect/Engineering

200,000

50,000

50,000

50,000

50,000

Construction - County Funded 2,000,000

500,000 500,000 500,000 500,000

Inspectors - County Project Management

100,000 100,000 150,000

25,000 25,000 37,500

25,000 25,000 37,500

25,000 25,000 37,500

25,000 25,000 37,500

Overhead

Total Cost:

2,550,000

637,500 637,500 637,500 637,500

Funding Schedule:

Project Total

Prior Budget

Categories

2026

2027

2028

2029

2030

2031 Costs After

Trans from W/S Cash Fund

2,550,000 2,550,000

637,500 637,500 637,500 637,500 637,500 637,500 637,500 637,500

Total Cost: