FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1091
Activity #:
Capital Project Title: SCDA Systems Upgrades
Region: Countywide
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2025 Est Completion Date: 6/30/2028
Capital Project Description: Upgrade to existing SCADA system to meet current standards. SCADA is a system to communicate the status of various water and sewer systems so that staff can monitor and operate the various equipment and systems. With newer technology and the addition of data points the existing SCADA system needs to be updated to address the additional data. These improvements are being coordinated with IIT.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Architect/Engineering
40,000 200,000 40,000 20,000 40,000 340,000
20,000
20,000
Construction - County Funded
100,000 100,000
Inspectors - County Project Management
20,000 10,000 20,000
20,000 10,000 20,000
Overhead
Total Cost:
170,000 170,000
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Trans from W/S Cash Fund
340,000 340,000
170,000 170,000 170,000 170,000
Total Cost:
167