FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1084
Activity #: 11559.1105.01
Capital Project Title: Water Meter Relocations
Region: Countywide
Capital Project Status: In Progress Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2023 Est Completion Date: 6/30/2027
Capital Project Description: The meters that are contained within these building all contains a meter room (where a main line comes into the building, manifolds into county owned individual meters for each condo/ apartment). The plumbing inside the meter room is currently mostly owned by the community ’ s HOA except from the meter holding device called a “ quarter horn ” which is part of the county ’ s property. We have discovered that most (if not all) of the internal plumbing lack any type of check or backflow prevention, allowing water to run the meter in a reverse water flow when a particular unit is vacant or doesn ’ t draw daily water usage. Briercrest Apartments, Spring Ridge Condos, Waterside Apartments, Stuart Mechanics Apartments,& Mountain Village Apartments.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Architect/Engineering 300,000 100,000 100,000 100,000 Construction - County Funded 1,580,800 520,000 530,400 530,400 Inspectors - County 150,000 50,000 50,000 50,000 Project Management 150,000 50,000 50,000 50,000 Overhead 150,000 50,000 50,000 50,000 Total Cost: 2,330,800 770,000 780,400 780,400
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Trans from W/S Cash Fund
2,330,800 770,000 780,400 780,400 2,330,800 770,000 780,400 780,400
Total Cost: