FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: WS1001
Activity #: 21483.1206.01
Capital Project Title: Ballenger-McKinney WWTP Sludge Management
Region: Countywide
Capital Project Status: Active Asset Type: Capacity Asset Category: Water & Sewer
Year Identified: 2010 Est Completion Date: 12/31/2028
Capital Project Description: This project was formally known as "McKinney WWTP Phase 1" and includes the design and construction of the first phase (15 MGD) sludge management improvements in accordance with the Ballenger Creek/McKinney WWTP Facility Plan dated March 2006. Per the Facility Plan, improvements are required when the average daily flow reaches 10 MGD. The City of Frederick's portion is assumed to be 17% of the project cost. The budget is being updated per the Ballenger McKinney WWTP Sludge Management Plan, prepared by WRA, dated August 2023.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Studies / Surveys
500,000 500,000
Architect/Engineering
15,775,580 500,000 742,080
14,533,500 96,890,000 29,067,000 19,378,000 29,067,000
Construction - County Funded 138,320,000 500,000 2,008,500 38,921,500
Inspectors - County Project Management
30,294,900 20,196,600 30,294,900
10,000 1,217,900 18,000 800,600 10,000 1,217,900
Overhead
Capitalized Interest Expense
0 Total Cost: 235,381,980 1,500,000 2,788,580 42,157,900
188,935,500
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Cap Contr - Municipal
39,929,937 170,000 500,000 500,000
7,640,902
32,119,035
Trans from W/S Cash Fund Enterprise Fund Bonds
194,952,043 830,000 2,788,580 34,516,998
156,816,465 188,935,500
Total Cost: 235,381,980 1,500,000 2,788,580 42,157,900
152