FY2026-FY2031 Proposed Capital Improvement Program

Capital Project Summary

Capital Project Number: BR1063

Activity #:

Capital Project Title: Bennies Hill Road Bridge Replacement (F03-22)

Region: Middletown

Capital Project Status: Active Asset Type: Bridges Asset Category: Bridges

Year Identified: 2024 Est Completion Date: 12/31/2032

Capital Project Description: Replace the current bridge, which was installed in 1982 with a large box culvert. Additional grading to assist water flow. Consultation will need to be done with Maryland Department of the Environment as the bridge is in the 100-year floodplain and studies will need to be performed on the hydrology.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2026

2027

2028

2029

2030

2031 Costs After

Studies / Surveys

22,000 10,200 145,700 728,300 51,000 36,500 993,700

22,000

Land

10,200 145,700

Architect/Engineering

Construction

728,300 51,000

Inspectors - County Project Management

36,500

Total Cost:

58,500 155,900

779,300

Funding Schedule:

Project Total

Prior Budget

Categories

2026

2027

2028

2029

2030

2031 Costs After

Trans from General Fund General Obligation Bonds

84,700 909,000 993,700

58,500

10,200 145,700

16,000 763,300 779,300

Total Cost:

58,500 155,900

132

Made with FlippingBook - Online magazine maker