Capital Project Summary
Capital Project Number: RD1080
Activity #:
Capital Project Title: Elmer Derr Road Realignment
Region: Adamstown
Asset Type: Roads Asset Category: Roads
Year Identified: 2022 Est Completion Date: 6/30/2035
Capital Project Status: Active
Capital Project Description: Resubmission
This project will improve portions of Elmer Derr Road and Cap Stine Road and construct a new alignment consistent with the proposed major arterial shown in the Comprehensive Plan. The project will connect the Mount Zion interchange on US15/340 with the Ballenger Creek Pike/English Muffin Way roundabout. The project includes construction of on-street bike lanes, geometric improvements, drainage improvements and other safety upgrades to meet current standards for an arterial roadway. Provision of a more direct link between US15/340 and the Ballenger Creek Pike corridor is believed to have the potential to reduce traffic volume on area roads, including the existing alignment of Elmer Derr Road and Cap Stine Road. The 2022 ADT on Cap Stine Road is 2,020 vehicles per day and the 2022 ADT on Elmer Derr Road is 3,841 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Studies / Surveys
226,800 599,400 179,900
226,800
Land
599,400 179,900
Site Improvement - NonBldg
Architect/Engineering Project Management
1,925,800
1,925,800
566,600
113,400 340,200
453,200
Total Cost:
3,498,500
3,158,300
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Trans from General Fund General Obligation Bonds
1,204,200 2,294,300 3,498,500
340,200
864,000
2,294,300 3,158,300
Total Cost:
340,200