FY2026-FY2031 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: RD1074
Activity #:
Capital Project Title: Old National Pike Corridor
Region: New Market
Asset Type: Roads Asset Category: Roads
Year Identified: 2022 Est Completion Date: 12/1/2033
Capital Project Status: Active
Capital Project Description: This project will improve the roadway from Bartholows Road east to the Mount Airy town limits. The project includes construction of on-street bike lanes, geometric improvements, drainage improvements and other safety upgrades to meet current standards for a minor arterial roadway. This corridor serves as an alternate route when incidents occur on I-70 between Mount Airy and New Market. The 2021 ADT on Old National Pike was 8,115 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Studies / Surveys
298,300 899,100
298,300
Land
899,100
Site Improvement - NonBldg
1,198,800 2,534,400 14,907,800
1,198,800
Architect/Engineering
2,236,200
298,200
Construction
14,907,800
Inspectors - County Project Management
894,600 223,800
894,600
223,800
Total Cost:
20,956,800
522,100 2,236,200 2,097,900 16,100,600
Funding Schedule:
Project Total
Prior Budget
Categories
2026
2027
2028
2029
2030
2031 Costs After
Trans from General Fund General Obligation Bonds
2,987,400 17,969,400 20,956,800
522,100 1,216,200 899,100 350,000
1,020,000 1,198,800 15,750,600
Total Cost:
522,100 2,236,200 2,097,900 16,100,600
110