FY2025 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: HW1001
Activity #: C6710.6710.01
Capital Project Title: Pavement Management Program
Region: Countywide
Capital Project Status: Active Asset Type: Highway Asset Category: Highways
Year Identified: 2010 Est Completion Date: 6/30/2030
Capital Project Description: The County's pavement network requires continuous monitoring, preventative maintenance, rehabilitation and reconstruction to ensure a safe and efficient transportation system. Funding is needed to execute this program so that our pavement network can continue to fulfill the needs of the travelling public. Typically, the funds will be used for the following contracts: patching, surface coat, overlay, cold-in-place recycling, full-depth reclamation, tar and chip sealing, and crack filling. **Prior budget is tracked in sub-projects**
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Construction
103,203,665
13,331,025 14,431,025 16,611,025 18,375,310 19,727,615 20,727,665 13,331,025 14,431,025 16,611,025 18,375,310 19,727,615 20,727,665
Total Cost: 103,203,665
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Trans from General Fund General Obligation Bonds
34,923,590 68,280,075
2,914,310 4,834,710 5,939,710 4,923,210 5,155,800 11,155,850 10,416,715 9,596,315 10,671,315 13,452,100 14,571,815 9,571,815 13,331,025 14,431,025 16,611,025 18,375,310 19,727,615 20,727,665
Total Cost: 103,203,665
140