FY2025 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: RD1081
Activity #:
Capital Project Title: Yellow Springs Road Improvements
Region: Frederick
Asset Type: Roads Asset Category: Roads
Year Identified: 2024 Est Completion Date: 12/31/2033
Capital Project Status: Active
Capital Project Description: This project will improve the portion of Yellow Springs Road between the Frederick City limits and Mountainview Drive. This project will including a new traffic signal at the intersection with Clover Hill Drive, sidewalks from the signal to the City limits, and road widening to include a center turn lane and paved shoulders to support an on-street bike way, drainage improvements and other safety upgrades. The 2023 ADT on this portion of Yellow Springs Road was 12,633 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Studies / Surveys
20,300 420,000 80,000 152,100
20,300
Land
420,000 80,000
Site Improvement - NonBldg
Architect/Engineering
152,100
Construction
1,013,500
1,013,500
Inspectors - County Project Management
60,900 50,700
60,900
50,700
Total Cost:
1,797,500
71,000 152,100 1,574,400
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Trans from General Fund General Obligation Bonds
71,000
71,000
1,726,500 1,797,500
152,100 1,574,400
Total Cost:
71,000 152,100 1,574,400