FY2025 Proposed Capital Improvement Program

Capital Project Summary

Capital Project Number: RD1076

Activity #:

Capital Project Title: New Design Road Corridor

Year Identified: 2022 Est Completion Date: Region: Adamstown

Asset Type: Roads Asset Category: Roads

Capital Project Status: Active

Capital Project Description: This project will improve the roadway section from Harshman Way south to MD 28. The project includes on construction of street bike lanes, geometric improvements, drainage improvements and other safety upgrades to meet current standards for an arterial roadway. The 2021 ADT at Harshman Way is 3,518 vehicles per day and the 2021 ADT near MD 28 is 4,072 vehicles per day. Construction could be completed in multiple phases depending on outcome of preliminary study.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2025

2026

2027

2028

2029

2030 Costs After

Studies / Surveys

857,584

857,584

Land

0 0

Site Improvement - NonBldg

Architect/Engineering

6,430,812

6,430,812

Construction

0 0

Inspectors - County Project Management

214,448

214,448

Total Cost:

7,502,844

7,502,844

Funding Schedule:

Project Total

Prior Budget

Categories

2025

2026

2027

2028

2029

2030 Costs After

Trans from General Fund General Obligation Bonds

1,072,032 6,430,812 7,502,844

1,072,032 6,430,812 7,502,844

Total Cost:

110