FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: HW1201
Activity #: C6770.6770.01
Capital Project Title: Cloverhill Stormdrain Improvements
Region: Frederick
Asset Type: Highway Asset Category: Highways
Year Identified: 2020 Est Completion Date: 12/1/2025
Capital Project Status: In Progress
Capital Project Description: This project will address the stormdrain culverts and associated drainage in the Cloverhill Development. Construction will include but not be limited to the installation of additional culverts, repairs to existing culverts, and modifications to the existing drainage swales, which will alleviate flooding concerns. Design and construction will coincide with the Office of Sustainability's Cloverhill Stormwater Retrofits project.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Site Improvement - NonBldg
100,000 500,000
100,000 500,000
Architect/Engineering
Construction
263,938 763,938 -675,000 175,000
Inspectors - County Project Management
250,000 150,000
250,000 75,000 500,000
75,000
Total Cost:
1,263,938 763,938
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
General Obligation Bonds
1,263,938 763,938 1,263,938 763,938
500,000 500,000
Total Cost:
177