FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: BR1058
Activity #:
Capital Project Title: Dollyhyde Road Bridge
Region: New Market
Capital Project Status: Active Asset Type: Bridges Asset Category: Bridges
Year Identified: 2019 Est Completion Date: 12/17/2030
Capital Project Description: Bridge No. F08-12. This project will replace the concrete bridge deck and steel beams and bearings on the Dollyhyde Road Bridge over North Fork Linganore Creek. The 2021 ADT at the bridge is 171 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Land
11,300 34,600 215,000 976,700 78,400 49,000
11,300 34,600
Site Improvement - NonBldg
Architect/Engineering
195,400
19,600 976,700 78,400
Construction
Inspectors - County Project Management
49,000 244,400
Total Cost:
1,365,000
45,900 1,074,700
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Federal Grants - Capital General Obligation Bonds
844,100 520,900
844,100
244,400 244,400
45,900 230,600 45,900 1,074,700
Total Cost:
1,365,000
161