FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: BR1032
Activity #: C6012.6012.01
Capital Project Title: Brethren Church Rd Br
Region: Middletown
Asset Type: Bridges Asset Category: Bridges
Year Identified: 2015 Est Completion Date: 12/15/2025
Capital Project Status: In Progress
Capital Project Description: Bridge No. F16-14. This project will replace an existing mutli-cell pipe structure over Catoctin Creek. The hydraulic opening is inadequate and traps debris, causing water to overtop the road. The 2022 ADT at the bridge is 532 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Land
60,000 38,800
60,000 38,800
Site Improvement - NonBldg
Architect/Engineering
644,500 583,500
61,000
Construction
3,051,000 2,700,000 351,000
Inspectors - County Project Management
152,500 135,000
17,500
43,800
43,800
Total Cost:
3,990,600 3,561,100 429,500
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Federal Grants - Capital Trans from General Fund General Obligation Bonds
2,073,700 2,073,700 431,000 431,000
1,485,900 1,056,400 429,500 3,990,600 3,561,100 429,500
Total Cost: