FY2023-FY2028 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG3005
Activity #: C4002.4002.01
Capital Project Title: Middletown Library Asset Type: Library Asset Category: General Government Capital Project Status: In Progress
Region: Middletown
Year Identified: 2017 Est Completion Date: 3/1/2023
Capital Project Description: This project replaces the Middletown Branch Library on Prospect Street with a new 15,250 s.f. library on a developer donated site on Green Street, west of the school complex. The Town will transfer the property to the County upon the County's request.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
NonCapital Furniture / Equipment
494,598 494,598
Site Improvement - NonBldg
122,599 122,599 662,418 662,418 7,893,783 7,893,783
Architect/Engineering
Construction
Construction - IIT Infrastruct
77,492 184,915 30,650 961,730 54,922
77,492 184,915
Inspectors - County Project Management
30,650
Capital - Furniture / Equipmen
961,730 54,922
Capital - IIT Hardware
Total Cost:
10,483,107 9,204,048 1,279,059
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
State Grants - Capital Trans from General Fund Trans from Impact Fee General Obligation Bonds
3,609,000 2,609,000 1,000,000
0
3,814,107 3,535,048 279,059
60,000
60,000
Impact Fee Bonds
2,850,357 2,850,357 149,643 149,643
Bond Premium / Discount
Total Cost:
10,483,107 9,204,048 1,279,059