Capital Project Number: FC5007

Activity #: C6508.6508.02

Capital Project Title: Technology Upgrade Asset Type: Community College Asset Category: Community College

Region: Frederick

Year Identified: 2010 Est Completion Date: 6/30/2026

Capital Project Status: Active

Capital Project Description: Upgrade PeopleSoft Student, HR, and Finance systems. *Prior Approval is tracked in a separate project

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2023

2024

2025

2026

2027

2028 Costs After

Capital Appropriations

2,708,302 908,302 300,000 300,000 300,000 300,000 300,000 300,000 2,708,302 908,302 300,000 300,000 300,000 300,000 300,000 300,000

Total Cost:

Funding Schedule:

Project Total

Prior Budget

Categories

2023

2024

2025

2026

2027

2028 Costs After

Trans from General Fund

2,708,302 908,302 300,000 300,000 300,000 300,000 300,000 300,000 2,708,302 908,302 300,000 300,000 300,000 300,000 300,000 300,000