FY2023-FY2028 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: BR1033
Activity #: C6009.6009.01
Capital Project Title: Hessong Bridge Road Bridge (F15-01)
Region: Thurmont
Asset Type: Bridges Asset Category: Bridges
Year Identified: 2010 Est Completion Date: 12/20/2026
Capital Project Status: In Progress
Capital Project Description: Bridge No. F15-01. This project will provide a new two-lane bridge to carry Hessong Bridge Road over Little Hunting Creek. It will also improve the roadway approaches to meet collector standards. The existing Acrow panel bridge only provides for one lane of traffic. This road is designated as a on-street bikeway. The 2022 ADT at the bridge is 683 vehicles per day.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Studies / Surveys
88,300
88,300
Land
120,000 120,000
Site Improvement - NonBldg
47,700
43,700
4,000
Architect/Engineering
1,015,600 812,100 203,500
Construction
3,505,000 1,598,800 280,400 126,800
1,906,200
Inspectors - County Project Management
153,600
140,200
67,900
72,300
Total Cost:
5,197,200 2,857,600 279,800 2,059,800
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Federal Grants - Capital Trans from General Fund General Obligation Bonds
4,240,700 2,430,100 162,800 1,647,800
46,200
46,200
910,300 381,300 117,000 412,000 5,197,200 2,857,600 279,800 2,059,800
Total Cost: