Capital Project Number: RD1076
Activity #:
Capital Project Title: New Design Road Corridor
Region: Adamstown
Asset Type: Roads Asset Category: Roads
Year Identified: 2022 Est Completion Date: 6/30/2036
Capital Project Status: Active
Capital Project Description: This project will improve the roadway section from Harshman Way south to MD 28. The project includes on construction of street bike lanes, geometric improvements, drainage improvements and other safety upgrades to meet current standards for an arterial roadway. The 2021 ADT at Harshman Way is 3,518 vehicles per day and the 2021 ADT near MD 28 is 4,072 vehicles per day. Construction could be completed in multiple phases depending outcome of preliminary study.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Studies / Surveys Project Management
729,700 182,400 912,100
729,700 182,400 912,100
Total Cost:
Funding Schedule:
Project Total
Prior Budget
Categories
2023
2024
2025
2026
2027
2028 Costs After
Trans from General Fund
912,100 912,100
912,100 912,100
Total Cost: