FY2023-FY2028 Adopted Capital Improvement Program
FY2023 - 2028 Adopted Capital Improvement Program Roads
Project
6-year
Total Project 14,678,400 11,680,000 2,739,200 16,482,100 8,936,700 8,557,500 4,836,700 1,460,000 656,400 17,233,600 3,664,700 912,100 91,837,400
Prior
2023
2024
Reichs Ford Road - Ph 2 Yeagertown Road
5,021,200 11,680,000 2,147,000 11,144,600 6,633,200 6,847,500 4,714,600 1,460,000 656,400 435,400 3,664,700 912,100 55,316,700
0 0
0 0 0
489,800 614,200
White Rock Subdivision Improvements Gas House Pike (from the City Limits to Boyers Mill Road)
592,200 5,337,500 2,303,500 1,710,000 122,100
0 0 0 0
11,144,600
Christopher's Crossing Widening Monrovia East-West Connector Braddock Heights Improvements
6,633,200 6,847,500 815,800 100,000
211,800 200,000 182,000
Artie Kemp Road Michaels Mill Road
0 0 0 0 0
0 0 0 0
Old National Pike Corridor Ballenger Creek Pike Corridor New Design Road Corridor
0 0 0
Total Expense
10,065,300
25,541,100
1,697,800
Funding General Fund
11,242,454 37,041,946 3,532,300 3,500,000 55,316,700
13,525,454 68,178,646 6,633,300 3,500,000 91,837,400
2,113,000 7,952,300
587,500 19,453,600 2,000,000 3,500,000 25,541,100
237,900 1,459,900
General Fund Bonds & Capital Leases
Grants Other
0 0
0 0
Total Funding Sources
10,065,300
1,697,800
134