FY2023 - 2028 Adopted Capital Improvement Program Watershed Restoration & Retrofit
Project
6-year
Total Project 13,531,554 12,055,521 20,048,385 23,806,787 626,610 10,053,667 80,122,524
Prior
2023
2024
County-Owned Stormwater Facility Retrofits
4,865,671 3,639,407 12,697,882 12,197,854 196,200 10,053,667 43,650,681
8,665,883 8,416,114 7,350,503 11,608,933
479,602 558,589 2,699,930 2,091,790
1,854,739 988,216
Reforestation Program Stream Restorations
66,644
Non-County Owned Stormwater Facility Retrofits
3,089,549
Watershed Assessments Watershed Systemics
430,410
196,200
0
0
0
1,199,000 7,198,148
Total Expense
36,471,843
6,026,111
Funding General Fund
7,470,627 36,180,054
21,351,156 57,131,523 1,639,845 80,122,524
13,880,529 20,951,469 1,639,845 36,471,843
376,200 5,649,911
180,000 7,018,148
General Fund Bonds & Capital Leases
Grants
0
0
0
Total Funding Sources
43,650,681
6,026,111
7,198,148
122