FY2023-FY2028 Adopted Capital Improvement Program
FY2023 Adopted Budget Capital Improvement Program
Parks & Recreation x Bikeways Trails Program This project includes trail development in corridors identified in the Frederick County Bikeways and Trails Plan. Included in FY23 is funding for two studies for Middletown/Myersville and Mount St. Mary s University/Emmitsburg. Design and construction are scheduled in alternating years. There are three major projects Frederick & Pennsylvania Line Railroad Trail (F&P Trail), New Design Road (NDR) Sidepath and H&F Trolley Trail (Thurmont to Catoctin Furnance). The chart below is a tentative schedule for the various phases of the Bikeways and Trails program.
FY2023
FY2024
FY2025
FY2026
FY2027
FY2028
F&P Trail Phase II design NDR Sidepath Phase I construction NDR Sidepath Phase II A design Study for Middletown/Myer sville potential trail Study for MSM University/Emmit sburg potential trail
NDR Sidepath Phase I construction H&F Trolley Trail Phase I design
F&P Trail Phase II construction F&P Trail Phase III design NDR Sidepath Phase II A construction
F&P Trail Phase II construction NDR Sidepath Phase II A construction NDR Sidepath Phase II B design H&F Trolley Trail Phase I construction
F&P Trail Phase III construction NDR Sidepath Phase II B construction H&F Trolley Trail Phase II design
F&P Trail Phase III construction NDR Sidepath Phase III design NDR Sidepath Phase II B construction H&F Trolley Trail Phase II construction
H&F Trolley Trail Phase I construction