Capital Project Summary
Capital Project Number: GG5008
Activity #: C2109.2109.01
Capital Project Title: Financial Systems Asset Type: Technology Asset Category: General Government
Region: Countywide
Year Identified: 2010 Est Completion Date: 6/30/2030
Capital Project Status: Active
Capital Project Description: This project supports software, hardware, and professional services to acquire, implement, and upgrade the Enterprise Resource Management System including financials, human resources, procurement, timesheets, treasury, and banking integration modules to ensure effective government financial accountability and management. **Prior Budget is tracked in a separate project**
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Project Management Capital - Software Capital - IIT Hardware
8,350,982 4,427,900
1,307,694
1,307,694
1,307,694
2,198,840 1,377,863 142,847 130,812 142,847 130,812 142,847 130,812
300,000 300,000
Total Cost:
10,849,822 6,105,763 142,847 1,438,506 142,847 1,438,506 142,847 1,438,506
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Trans from General Fund General Obligation Bonds
10,464,682 5,720,623 142,847 1,438,506 142,847 1,438,506 142,847 1,438,506
385,140 385,140
Total Cost:
10,849,822 6,105,763 142,847 1,438,506 142,847 1,438,506 142,847 1,438,506