Capital Project Number: GG3006
Activity #:
Capital Project Title: Linganore Town Center Library
Region: New Market
Asset Type: Library Asset Category: General Government
Year Identified: 2017 Est Completion Date: 12/1/2030
Capital Project Status: Active
Capital Project Description: This project constructs a single-story 25,000 s.f. library off MD RT 144, convenient to the Oakdale Elementary School. This East County Regional Library will provide library service to Spring Ridge, Lake Linganore, New Market, and Monrovia, areas currently without library service.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Site Improvement - NonBldg
31,000
31,000
Architect/Engineering
1,269,200 12,692,000
1,269,200
Construction
12,692,000
Construction - IIT Infrastruct
123,500 201,200
123,500 201,200 36,900
Inspectors - County Project Management
75,600
38,700
Capital - Furniture / Equipmen 7,392,600
3,696,300 3,696,300
Capital - IIT Hardware
87,700
87,700
Total Cost:
21,872,800
1,338,900
16,837,600 3,696,300
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
State Grants - Capital Trans from Impact Fee General Obligation Bonds
3,800,000 3,145,185 11,927,615 3,000,000 21,872,800
400,000 645,185 293,715
2,000,000 1,400,000 2,000,000 500,000 9,837,600 1,796,300
Impact Fee Bonds
3,000,000
Total Cost:
1,338,900
16,837,600 3,696,300