FY2025 Proposed Capital Improvement Program

Capital Project Summary

Capital Project Number: WS1088

Activity #: 21533.1206.01

Capital Project Title: Buckeystown interceptor Sewer Rehabilitation

Region: Frederick

Capital Project Status: In Progress Asset Type: Capacity Asset Category: Water & Sewer

Year Identified: 2023 Est Completion Date: 6/30/2026

Capital Project Description: Project includes design, bidding, inspection, and construction services required to rehabilitate approximately 11, 65- L.F. of 30-inch DIP sewer with cured in place pipe (CIPP) lining.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2025

2026

2027

2028

2029

2030 Costs After

Architect/Engineering

272,200

35,000 215,600

21,600

Construction - County Funded 2,405,000

2,405,000

Inspectors - County Project Management

188,000 41,001 187,998

188,000 13,667 62,666

13,667 62,666

13,667 62,666

Overhead

Total Cost:

3,094,199

111,333 291,933 2,690,933

Funding Schedule:

Project Total

Prior Budget

Categories

2025

2026

2027

2028

2029

2030 Costs After

Trans from W/S Cash Fund Enterprise Fund Bonds

2,784,330

111,333 291,933 2,381,064

309,869

309,869

Total Cost:

3,094,199

111,333 291,933 2,690,933

162