FY2025 Proposed Capital Improvement Program
Capital Project Summary
Capital Project Number: BR1049
Activity #: C6015.6015.01
Capital Project Title: Stottlemeyer Road Bridge Deck Replacement
Region: Middletown
Asset Type: Bridges Asset Category: Bridges
Year Identified: 2018 Est Completion Date: 12/13/2025
Capital Project Status: In Progress
Capital Project Description: Bridge F06-01. This project will replace the deteriorating concrete bridge deck and joints on Stottlemeyer Road over Middle Creek. Painting of structural steel is also included in the work. The 2021 ADT at the Stottlemeyer Road Bridge is 1,283 vehicles per day. The bridge was built in 1977.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Land
10,000 26,400
10,000 26,400
Site Improvement - NonBldg
Architect/Engineering
232,528 211,000
21,528
Construction
1,075,880
1,075,880
Inspectors - County
154,232
67,600
86,632
Total Cost:
1,499,040 315,000 1,184,040
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Federal Grants - Capital Trans from General Fund General Obligation Bonds
901,600 77,600
7,400 894,200
72,500
5,100
519,840 235,100 284,740 1,499,040 315,000 1,184,040
Total Cost:
123