FY2025 Proposed Capital Improvement Program

Capital Project Summary

Capital Project Number: BR1033

Activity #: C6009.6009.01

Capital Project Title: Hessong Bridge Road Bridge (F15-01)

Region: Thurmont

Asset Type: Bridges Asset Category: Bridges

Year Identified: 2010 Est Completion Date: 12/20/2026

Capital Project Status: In Progress

Capital Project Description: Bridge No. F15-01. This project will provide a new two-lane bridge to carry Hessong Bridge Road over Little Hunting Creek. It will also improve the roadway approaches to meet collector standards. The existing Acrow panel bridge only provides for one lane of traffic. This road is designated as a on-street bikeway. The 2022 ADT at the bridge is 683 vehicles per day.

Cash Requirement Schedule:

Project Total

Prior Budget

Categories

2025

2026

2027

2028

2029

2030 Costs After

Studies / Surveys

88,300

88,300

Land

135,600 135,600

Site Improvement - NonBldg

53,900

53,900

Architect/Engineering

1,221,008 1,096,000 125,008 4,200,672 1,598,800 2,601,872 335,008 126,800 208,208

Construction

Inspectors - County Project Management

240,300 240,300

Total Cost:

6,274,788 3,339,700 2,935,088

Funding Schedule:

Project Total

Prior Budget

Categories

2025

2026

2027

2028

2029

2030 Costs After

Federal Grants - Capital Trans from General Fund General Obligation Bonds

4,818,700 2,657,200 2,161,500

92,447

92,447

1,363,641 590,053 773,588 6,274,788 3,339,700 2,935,088

Total Cost: