FY2025-FY2030 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG2019
Activity #: C5001.5001.01
Capital Project Title: Courthouse Capacity Improvements Project
Region: Frederick
Capital Project Status: In Progress Asset Type: Other Asset Category: General Government
Year Identified: 2016 Est Completion Date: 6/30/2032
Capital Project Description: Addressing space limitations at the Frederick County Courthouse was a priority identified in the 2013 Countywide Synergy and Efficiency Concept Plan, and the Administrative Office of the Court's Workload Analysis for FY2015 confirmed the need for additional Circuit Court space. This project adds approximately 115,000 sq.ft. with an addition behind the existing Courthouse.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Studies / Surveys
155,092 155,092
NonCapital Furniture / Equipment
1,082,625
1,082,625
Site Improvement - NonBldg
2,524,986 1,262,493
1,262,493
Architect/Engineering
3,170,350 2,170,350 1,000,000
Construction
76,527,567
7,200,000 69,327,567
Construction - IIT Infrastruct
360,875
360,875 150,000 40,000
Inspectors - County Project Management
320,088 170,088
170,118
67,625
62,493
Capital - Furniture / Equipmen 1,082,625
1,082,625
Capital - IIT Hardware
360,875
360,875
Total Cost:
85,755,201 3,825,648 1,000,000
7,262,493 73,667,060
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After 2,262,493 3,262,493 5,000,000 70,404,567 7,262,493 73,667,060
Trans from General Fund General Obligation Bonds
5,966,623 321,637 120,000 79,788,578 3,504,011 880,000 85,755,201 3,825,648 1,000,000
Total Cost:
72