FY2025-FY2030 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: WR1026
Activity #: C8009.8009.01
Capital Project Title: County-Owned Stormwater Facility Retrofits Asset Type: Watershed Restoration & Retrofit Asset Category: Watershed Restoration & Retrofit
Region: Countywide
Year Identified: 2015 Est Completion Date: 12/28/2029
Capital Project Status: In Progress
Capital Project Description: This project provides design and construction funds for recommended retrofits identified by assessments of County owned Properties and Stormwater Management Best Management Practices, and from other site investigations performed as part of the County's NPDES MS4 Permit operations. The subprojects identified under this project are locations where there is little to no stormwater runoff control or treatment, where retrofit of the facility by the County can receive impervious surface crediting towards the NPDES MS4 permit, and where the impervious surface credit return on investment is maximized. Subprojects under this project anticipated to be completed include Clover Hill Stormwater Pond retrofit.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
Salary & Wages
31,488 19,210
31,488 19,210
Land
Site Improvement - NonBldg
389,054 243,454 2,514,581 2,412,381
45,300
74,800
25,500
Architect/Engineering
102,200
Construction
9,870,983 7,298,483 566,200
1,655,000
351,300 32,000 10,600
Inspectors - County Project Management
601,899 417,999 354,221 252,921
56,600 18,900
95,300 61,200
10,600
Total Cost:
13,781,436 10,675,936 687,000
1,886,300 112,800 419,400
Funding Schedule:
Project Total
Prior Budget
Categories
2025
2026
2027
2028
2029
2030 Costs After
State Grants - Capital Trans from General Fund General Obligation Bonds
291,055 291,055 2,365,608 2,365,608
11,124,773 8,019,273 687,000 13,781,436 10,675,936 687,000
1,886,300 112,800 419,400 1,886,300 112,800 419,400
Total Cost: