Capital Project Number: GG3009
Activity #:
Capital Project Title: C Burr Artz Library Remodel
Region: Frederick
Asset Type: Library Asset Category: General Government
Year Identified: 2021 Est Completion Date: 12/31/2030
Capital Project Status: Active
Capital Project Description: This project allows for a major renovation of the C. Burr Artz Library in downtown Frederick. Built in 2002, the current 65K SF facility houses 20K SF of space for the systems ’ Administrative offices. It serves as the central branch, welcoming just under 400K customers each year. In order to maximize public space, this renovation should occur after construction of a new North Frederick facility which will move the Administrative offices out of their current location allowing all 65K SF for public use. This renovation will include: updates to the exterior of the building, a complete transformation to the interior layout and finishes, and new mechanical and electrical systems.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
NonCapital Furniture / Equipment Architect/Engineering
1,014,552
1,014,552
2,029,104 20,291,031
2,029,104
Construction
20,291,031
Construction - IIT Infrastruct
158,800 250,000 100,000
158,800 250,000 50,000
Inspectors - County Project Management
50,000
Capital - Furniture / Equipmen 1,014,552
1,014,552
Capital - IIT Hardware
158,800
158,800
Total Cost:
25,016,839
2,079,104 22,937,735
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After 500,000 1,500,000 1,579,104 21,437,735 2,079,104 22,937,735
State Grants - Capital General Obligation Bonds
2,000,000 23,016,839 25,016,839
Total Cost:
82