FY2024-FY2029 Adopted Capital Improvement Program
Capital Project Summary
Capital Project Number: GG3006
Activity #:
Capital Project Title: Linganore Town Center Library
Region: New Market
Asset Type: Library Asset Category: General Government
Year Identified: 2017 Est Completion Date: 12/1/2028
Capital Project Status: Active
Capital Project Description: This project constructs a single-story 25,000 s.f. library off MD RT 144, convenient to the Oakdale Elementary School. It will provide library service to Spring Ridge, Lake Linganore, New Market, and Monrovia, areas currently without library service.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Site Improvement - NonBldg
29,765
29,765
Architect/Engineering
1,220,382 12,203,817
1,220,382
Construction
12,203,817
Construction - IIT Infrastruct
118,764 193,475
118,764 193,475 35,436
Inspectors - County Project Management
72,644
37,208
Capital - Furniture / Equipmen 3,554,177
3,554,177
Capital - IIT Hardware
84,312
84,312
Total Cost:
17,477,336
1,287,355
16,189,981
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
State Grants - Capital Trans from Impact Fee General Obligation Bonds
3,800,000 3,145,185 7,532,151 3,000,000 17,477,336
400,000 645,185 242,170
3,400,000 2,500,000 7,289,981 3,000,000 16,189,981
Impact Fee Bonds
Total Cost:
1,287,355
79