FY2024-FY2029 Adopted Capital Improvement Program
FY2024 Adopted Budget Capital Improvement Program
Summary of Changes
Current Construction Year
CE Proposed Construction Year
Project #
ROADS Project Name
Notes
RD1061 Reichs Ford Road - Ph 2 RD1064 Yeagertown Road
2029 2028 2025 2023 2025 2026 2026
2030 2029 2025
Delayed 1 year Delayed 1 year
RD1066 White Rock Subdivision Improvements
No Change
Gas House Pike (from the City Limits to Boyers Mill Road)
RD1067
2023/24 Residual funding
RD1070 Braddock Heights Improvements RD1072 Artie Kemp Road RD1073 Michaels Mill Road RD1074 Old National Pike Corridor
2027 2026 2026
Delayed 2 years
No Change No Change No Change
Study: 2028; Design 2029 Study: 2026 Design: 2028 Study: 2027 Design: 2029
Study: 2028; Design 2029 Study: 2026 Design: 2028 Study: 2027 Design: 2029 Study: 2027 Design: 2028 Study: 2028 Design: 2029
RD1075 Ballenger Creek Pike Corridor
No Change
RD1076 New Design Road Corridor
No Change
RD1077 *Improvements to Urbana Pike
New Project
RD1078 *Bethel Road Improvements
New Project New Project
RD1079 *Mountville Road Streetscape
2026
Current Construction Year
CE Proposed Construction Year
Project #
BRIDGES Project Name
Notes
BR1032 Brethren Church Rd Br
2022/23 2021-24
2022-24 Residual funding
BR1033 Hessong Bridge Road Bridge (F15-01) BR1038 Biggs Ford Road Bridge F26-04 BR1049 Stottlemeyer Road Bridge Deck Replacement BR1051 Replacement of Old Mill Road Bridge over Maryland Midland Railroad
2021-25 Residual funding: per division delay 1 year
2025 2024 2023 2026 2027 2028 2024 2027
2025 2025
No Change Delayed 1 year
2023/24 Residual funding
BR1052 Sixes Bridge Road Bridge BR1053 Oppossumtown Pike Bridge
2026 2027 2028 2024 2027
No Change No Change No Change No Change No Change No Change No Change
BR1054 Lynn Burke Road Bridge Replacement
BR1055 Covell Road Bridge BR1056 Holter Road Bridge
BR1057 Hessong Bridge Road Bridge (F20-21) BR1058 Dollyhyde Road Bridge BR1059 Bridge at Prices Distillery Road BR1060 *Bullfrog Road Bridge F05-06 BR1061 *Loys Station Covered Bridge F04-02
Out Years Out Years Out Years
Out Years Out Years
Out Years No Change Design: 2029 New Project Design: 2029 New Project
BR1062 *Park Mills Road Culvert
2028
New Project
Current Construction Year
CE Proposed Construction Year
Project #
HIGHWAYS Project Name
Notes
HW1001 Pavement Management Program
Reduced FY24 funding: Adjusted funding between fiscal years
On-Going On-Going Various
On-Going
HW1050 Highway Network Systemic - General HW1090 Sidewalk Retrofit Program HW1095 Pedestrain and Bicycle Missing Links HW1201 Cloverhill Stormdrain Improvements HW1202 Drainage Assessment Response Team (DART) HW3002 Thurmont & Johnsville Satellite Facility Improvements HW1101 Traffic Control and Safety
On-Going Partial additional funding in FY24-29
Various
No Change
2023
2023/24 Residual funding
Various
Various
No Change
2022
2022/2025 Residual funding
Various
Various
No Change
2025 2029
2027 2030
Delayed 2 years Delayed 1 year
HW3006 Frederick Satellite Yard HW3007 Intercoastal Drive Brine Systems
2022/2024
2022/2024 Residual funding
GREEN Additional funding added or New Project ORANGE Partial request funded RED Project delayed
* Denotes "New" project