Capital Project Number: WS1087
Activity #: 11532.1105.01
Capital Project Title: Refurbish Bolted Steel Water Tanks
Region: Countywide
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2023 Est Completion Date: 6/30/2028
Capital Project Description: Project will refurbish the interior and exterior of glass lined bolted steel tanks to extend the useful life. Includes repairs, cleaning of seams, bolt replacements, etc. Inspection reports for fourteen (14) tanks will be reviewed to establish an order of priority for the following tanks: Bradford Estates, Cloverhill III, Copperfield WTP, Fountaindale, Fountaindale WTP, Libertytown East, New Market West, Nightingale, Samhill, Waterside, White Rock 1, White Rock 2, Windsor Knolls and Woodspring. Provision for storage and pressure during construction is needed to maintain the existing water systems (excluding offline and unused tanks- Cloverhill III, New Market West, Waterside and Woodspring).
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Architect/Engineering
500,000
100,000 100,000 100,000 100,000 100,000 500,000 500,000 500,000 500,000 500,000
Construction - County Funded 2,500,000
Inspectors - County Project Management
250,000 250,000 250,000
50,000 50,000 50,000
50,000 50,000 50,000
50,000 50,000 50,000
50,000 50,000 50,000
50,000 50,000 50,000
Overhead
Total Cost:
3,750,000
750,000 750,000 750,000 750,000 750,000
Funding Schedule:
Project Total
Prior Budget
Categories
2024
2025
2026
2027
2028
2029 Costs After
Trans from W/S Cash Fund
3,750,000 3,750,000
750,000 750,000 750,000 750,000 750,000 750,000 750,000 750,000 750,000 750,000
Total Cost: